Current Position: Head of Capital Projects at Southampton Airport.
NEC Experience: AGS – Southampton International Airport
HEAD OF CAPITAL PROJECTS December 2013 – Present.
Responsible for the delivery of the Southampton Airport’s Capital Projects Portfolio. Projects ranging from terminal developments, Airport infrastructure, major construction works and IT projects.
Utilising the NEC Suite of Contracts to deliver the Airports Capital Projects including Principal & Sub Contracts, Design team consultants and direct Capital Purchases.
Primary Contract Suites are as follows –
Option A – With Activity Schedule
Option C With Activity Schedule
Option E
Professional Services Contracts.
Direct report to Managing Director; Produce and present Monthly AGS Capital Projects board reports.

Anesco Energy Services Limited
HEAD OF ESCO - November 2012 – December 2013
Responsible of the leadership and management of the Energy Efficiency Delivery team. The team includes Energy Efficiency Managers, Project Managers, Design Consultants and Biomass Managers. Successfully delivered the first UK ESCO multi energy saving project for Mid Devon Council.

BAA Southampton Airport – Southampton
PROJECTS MANAGER - March 2006 – November 2012.
Responsible for the delivery of the Southampton Airport’s Capital Projects Portfolio. Strong safety record with no reportable accidents in over four years and all projects delivered within the airport facility and public interface areas. Responsible for organising and facilitating Capital and Engineering Health & Safety, Project Steering / Operating Committees meetings.
NEC Projects: New Fire Training Simulator Rig - NEC 3 – Option A -Head of Capital Projects - £1,300,000 - March 2015 - October 2015
Runway Approach lighting - NEC 3 - Option A - Head of Capital Projects - £455,00 - October 2014 - January 2015
Terminal Replacement Glazing - NEC 3 Option A - Projects Manager - £1,250,000 - February 2009 - April 2009
Terminal Retail Development - NEC 3 Option A - Projects Manager - £1,350,000 - April 2009    October 2009
Airport Small works portfolio - NEC 3 Option E - Head of Capital Projects - £550,000 - January 2014 - December 2015
New Aircraft stands - NEC 3 Option A - Head of Capital Projects - £375,000 - October 2014 - March 2015
Runway Drainage    NEC 3 Option C - Head of Capital Projects - £2,500,000 - September 2015 - August 2016
ESCO multi energy saving project - NEC 3 Option A - Head of ESCO - £450,000 - December 2012 - March 2013
Multi Storey Car Park Extension - NEC 3 D&B - Projects Manager 0- £675,000 - April 2008 - November 2009
Various Terminal & Airside developments - NEC 3 Option A&E - Projects Manager - Ranging from £100,000- £300,000 - April 2007 - November 2012
Runway Ground lighting replacement - NEC 3 Option A - Head of Capital Projects - £175,000 - August 2015- October 2015
Airport baggage system - NEC 3; D&B - Head of Capital Projects - £2,230,000 - September 2015 - March 2017